The Grosvenor Hotel/Edinburgh

Decommission of 174 guestrooms from this iconic Edinburgh Hotel. Working to a circular reuse strategy for all redundant resources on this project.

Client

Chandler KBS​

​

Contribution

FF+E Decommission + Reuse strategy

​

Timeline

Oct 2021 - Dec 2022

The Grosvenor Hotel.jpg

The Brief:

 

The client encountered a last minute change to the project planning with regards to the decommission strategy for redundant FF+E in this 174 guestroom hotel. BGES were offered a very short three day planning and mobilisation period before works were to begin. All FF+E was to be removed from guestrooms in one phase of work. The client requested the implementation of reuse strategy for all redundant FF+E.

The Outcome:

 

174 guestrooms decommissioned during a 6 week window to allow the main contractor to begin the remodelling/renovation schedule. BGES would work to a program of remove to reuse. Approx. 3100 individual pieces of FF+E were removed from site.

CSR & Sustainability

 

During asset decommission works, BGES adhered to circular strategies for resource reuse created and managed by sustainability partners - Recreate Scotland. The Grosvenor hotel and associated project management at ChandlerKBS are Recreate Certified organisations having made the commitment to reduce their carbon footprint during periods of resource decommission/renovation.

Zero skips were utilised for loose FF+E during the decommission program and an impressive reuse rate of 72% was achieved for all redundant FF+E. Read more about their sustainability credentials here.